BlueCielo Meridian Enterprise 2013 User's Guide | BlueCielo ECM Solutions

You are here: Working with documents > Viewing prior revisions > Creating a baseline

Creating a baseline

To create a baseline:

  1. View the vault at the moment in time for which you want to create the baseline.
  2. Click Baselines on the Vault menu. The Baselines dialog box appears.
  3. Click the New button . A new baseline is added to the list.
  4. Type a name for the baseline and press Type.
  5. Click Close.

You can now view this baseline at any time by selecting it either in the Baselines dialog or from the list shown by clicking the context button on the context bar.

Related tasks

Viewing prior revisions

Viewing vault history

Comparing documents

Comparing document property values

Printing documents


Copyright © 2000-2013 BlueCielo ECM Solutions

www.bluecieloecm.com